Mount Mackenzie Proposed Phase 1A Runs/Lift Approval/Cutting Schedule
 

  • Mount Mackenzie Resort Ltd. to flag the boundaries of the ski runs and lift line
    September 2003
     
  • Downie Timber Ltd. To conduct a preliminary field survey of the ski runs/lift line and determine their interest in cutting the timber
    September 2003
     
  • Downie Timber Ltd. completes a timber cruise and geotechnical assessment and prepares valuation/assessment report for submission to the ministry of forests
    September-October 2003
     
  • Ministry of Forests conducts field check and accepts Downie valuation/assessment
    • Land and Water BC survey controlled recreation boundary
      October-November 2003
       
  • Land and Water BC review and approve Master plan
    December-February 2004
     
  • Ministry of Forests approves cutting plan
    February-March 2004
     
  • Downie begins to cut ski runs/lift line
    May-June 2004

 


The City of Revelstoke
Box 170 - 216 Mackenzie Avenue
Revelstoke BC Canada V0E 2S0
Phone: (250) 837-2161  Fax: (250) 837-4930

 
© 2000 - 2008 The City of Revelstoke (Website Disclaimer)

[Home Page]

 

Website designed & maintained by:
Click Here To Visit Solutions Interactive WebSite
Contact Webmaster